Mitsui & Co., Ltd ("Mitsui", head office: Tokyo, President & CEO; Masami Iijima), has agreed with GDF SUEZ Canada Inc. ("GDFS-C"), part of the global energy group GDF SUEZ S.A., to participate in the renewable energy power generation projects in Canada ("Project") currently developed and operated by GDF SUEZ Canada. Mitsui, through MIT Renewables Inc. ("MIT-RE"), its newly established subsidiary, has acquired 30% ownership of this Project, which is valued in excess of C$ 2 billion.
As summarized in the table below, the Project is composed of 10 wind farms totaling 660 MW and 2 solar photovoltaic power plants totaling 20MW nationwide in Canada, selling the electricity in accordance with long term power purchase agreements with respective provincial electric utilities. Among the 12 projects, 7 wind farms have started commercial operation and the other 5 projects are currently under development or construction. In addition, there is an expansion opportunity under development to add approximately 50 MW to an existing site to bring the total generation capacity of the project portfolio to 730 MW. The Project contributes to energy saving and environmental improvement as well as stable power supply in Canada, including the Province of Ontario, which promotes clean energy with its significant commitment to renewable energy.
A loan agreement on a project finance basis has been executed for the 5 projects under development or construction including the aforementioned expansion opportunity, with Japan Bank for International Cooperation ("JBIC") and a group of commercial banks composed of The Bank of Tokyo-Mitsubishi UFJ, Ltd., Mizuho Corporate Bank and Sumitomo Mitsui Banking Corporation on December 14 ("JBIC Facility").
GDFS-C has also simultaneously completed a sale of another 30% ownership of this Project to a consortium led by the Canadian infrastructure fund, Fiera Axium Infrastructure Inc. ("Fiera Axium"), and from now on GDFS-C, MIT-RE and Fiera Axium together will own, operate and develop the Project.
Mitsui will contribute to the development and operation of the Project by leveraging its expertise from its abundant experience in the overseas power business. With the participation in this Project, Mitsui now holds approximately 5,761MW, on an installed generating capacity basis, including projects under construction, out of which 380MW comes from renewable energy, accounting for approximately 7% of the above generating capacity. Amid the growing need for renewable energy in view of sustainability and reduction of carbon dioxide emissions, Mitsui will further pursue renewable energy projects in Canada and elsewhere, thereby contributing to the development of a low-carbon social infrastructure.
Project overview
1) Ownership
| GDF SUEZ Canada | 40% |
|---|---|
| MIT Renewables | 30% |
| Fiera Axium | 30% |
2) Project List
| Project Name | Province(*1) | Type | COD(*2) | Installed Capacity | Joint Venture Ownership | Remarks |
|---|---|---|---|---|---|---|
| Norway | PEI | Wind | 2007 | 9MW | 100% | Under commercial operation |
| SOP | ON | Wind | 2008 | 40MW | 100% | Under commercial operation |
| West Cape | PEI | Wind | 2009 | 99MW | 100% | Under commercial operation |
| Caribou | NB | Wind | 2009 | 99MW | 100% | Under commercial operation |
| Harrow | ON | Wind | 2010 | 40MW | 100% | Under commercial operation |
| PAR | ON | Wind | 2011 | 49MW | 100% | Under commercial operation |
| Plateau | ON | Wind | 2012 | 27MW | 100% | Under commercial operation |
| ELSC | ON | Wind | 2013E | 99MW | 100% | Under construction |
| Erieau | ON | Wind | 2013E | 99MW | 100% | Under construction Covered by JBIC Facility |
| Cape Scott | BC | Wind | 2013E | 99MW | 100% | Under construction Covered by JBIC Facility |
| Cape Scott Expansion (*3) | BC | Wind | 2014E | 50MW | 100% | Under development Covered by JBIC Facility |
| Brockville | ON | Solar PV | 2013E | 10MW | 60%(*4) | Under construction Covered by JBIC Facility |
| Beckwith | ON | Solar PV | 2014E | 10MW | 60%(*4) | Construction to start in Q2 2013 Covered by JBIC Facility |
| Total | 730MW | |||||
*1 PEI: Prince Edward Island, ON: Ontario, NB: New Brunswick, BC: British Columbia
*2 Commercial Operation Date ("COD")
*3 Expansion opportunity under development at the Cape Scott site to add incremental 50 MW of capacity
*4 Plan to buy out the minority shareholder's ownership of 40% at COD
GDF SUEZ
| Company | GDF SUEZ S.A. |
|---|---|
| Head Quarter | Paris, France |
| President | Gérard Mestrallet (Chairman & CEO) |
| Business | Electricity, natural gas, and energy and environmental services |
| Foundation date | July, 2008 |
Fiera Axium
| Company | Fiera Axium Infrastructure Inc. |
|---|---|
| Head Quarter | Montreal, Canada |
| President | Pierre Anctil (President & CEO) |
| Business | Investment in infrastructure sector |
| Foundation date | July, 2008 |
Investment Structure

Photo of Norway Wind Project

Notice:
This announcement contains forward-looking statements. These forward-looking statements are based on Mitsui's current assumptions, expectations and beliefs in light of the information currently possessed by it and involve known and unknown risks, uncertainties and other factors. Such risks, uncertainties and other factors may cause Mitsui's actual results, financial position or cash flows to be materially different from any future results, financial position or cash flows expressed or implied by these forward-looking statements. These risks, uncertainties and other factors referred to above include, but are not limited to, those contained in Mitsui's latest Annual Securities Report and Quarterly Securities Report, and Mitsui undertakes no obligation to publicly update or revise any forward-looking statements.
This announcement is published in order to publicly announce specific facts stated above, and does not constitute a solicitation of investments or any similar act inside or outside of Japan, regarding the shares, bonds or other securities issued by us.
For inquiries on this matter, please contact
Mitsui & Co., Ltd.
Corporate Communications Division
Toshie Kyo
Telephone: +81-3-3285-7596
Facsimile: +81-3-3285-9819
The information contained in this news release is true and accurate at the time of publication; however, it may be subject to change without prior notice.